Planned this week:
Sewer, water line installation, drainage system work
Nov. 8: Day 200 of 820
Start date: April 23, 2012
End date: Aug. 20, 2014
Percent complete: 24.4%
Holiday/rain days: 26
Storm days: 2
For more information, visit www.fdotmonroe.com/keywest or contact spokesman Dean Walters at dean@swcinc.net or 305-849-1474