Florida Keys News - Key West Citizen
Wednesday, November 14, 2012
Boulevard Project Update NOV. 8-14

Planned this week:

Sewer, water line installation, drainage system work

Nov. 8: Day 200 of 820

Start date: April 23, 2012

End date: Aug. 20, 2014

Percent complete: 24.4%

Holiday/rain days: 26

Storm days: 2

For more information, visit www.fdotmonroe.com/keywest or contact spokesman Dean Walters at dean@swcinc.net or 305-849-1474

More Florida Keys Headlines
Available Only in the Electronic Edition
Friday, December 9, 2016 -
Thursday, December 8, 2016 -
Wednesday, December 7, 2016 -
Wednesday, December 7, 2016 -
Tuesday, December 6, 2016 -
Monday, December 5, 2016 -