BOULEVARD PROJECT UPDATE DEC. 6-13

Planned this week:

Sewer, water line installation, decontamination, drainage system work continues. No work will take place from Dec. 22 to Jan. 2.

Dec. 6: Day 228 of 820

Start date: April 23, 2012

End date: Aug. 23, 2014

Percent complete: 27.8%

Holiday/rain days: 7/26

Storm days: 2

Nighttime work: 8 p.m. to 5 a.m. at Sigsbee Base entrance through Dec. 10

This week's FAQ:

How did this project get started, and why will it take so long?

The project, and all its revisions and permits, has taken over 10 years to develop. It will take so long because four elements are involved: sewer, water, drainage and the seawall. The original timeline was 1,200 days, about 3¬½ years, but FDOT worked with the city of Key West and the Chamber of Commerce to reduce it to 820 days, affecting two tourist seasons instead of three. The reduction was made possible by giving the contractor more leeway, allowing work to proceed to the next sequence of the project when one of the four elements is completed in the prior.

The state also added a $10,000 per day incentive for early completion, which adds up to $1.2 million if the project is done in 700 days.

There are financial penalties for late completion, also at $10,000 a day, plus damages of an additional $6,800 a day.

For more information, visit www.fdotmonroe.com/keywest or contact spokesman Dean Walters at dean@swcinc.net or 305-849-1474.

More Florida Keys Headlines
Monday, October 20, 2014
Monday, October 20, 2014
Monday, October 20, 2014
Sunday, October 19, 2014
Sunday, October 19, 2014
Available Only in the Electronic Edition
Monday, October 20, 2014 -
Sunday, October 19, 2014 -
Saturday, October 18, 2014 -
Friday, October 17, 2014 -
Thursday, October 16, 2014 -
Wednesday, October 15, 2014 -