Google+
Florida Keys News - Key West Citizen
Sunday, March 10, 2013
BOULEVARD PROJECT UPDATE MARCH 7-14

Planned this week:

Seawall construction and drainage system installation continues. The sidewalk/promenade is closed; all bicyclists and pedestrians must use the dedicated path separated by concrete barrier and fencing.

March 7: Day 319 of 820

Start date: April 23, 2012

End date: August 2014

Percent complete: 36.8%

This week's FAQ:

Are they hiring local workers?

The contractor is required to hire at least 12 trainees for the project. The best way to do this is to hire from the local community, says FDOT. If no locals qualify, other sources will be used. Anyone wishing to qualify may download employment information and an application from www.fdotmonroe.com/keywest and come to the construction office, 3142 Boog Powell Court, Key West.

For more information, visit www.fdotmonroe.com/keywest or contact spokesman Dean Walters at dean@swcinc.net or 305-849-1474.

More Florida Keys Headlines
Wednesday, October 22, 2014
Wednesday, October 22, 2014
Wednesday, October 22, 2014
Wednesday, October 22, 2014
Available Only in the Electronic Edition
Wednesday, October 22, 2014 -
Wednesday, October 22, 2014 -
Tuesday, October 21, 2014 -
Monday, October 20, 2014 -
Sunday, October 19, 2014 -
Saturday, October 18, 2014 -