Planned this week:
No work through Jan. 2 for
holiday break.
Dec. 20: Day 248 of 820
Start date: April 23, 2012
End date: August 2014
Percent complete: 29.5%
Holiday/rain days: 7/26
Storm days: 2
This week's FAQ:
What kind of work is being done?
The North Roosevelt Boulevard project includes:
• Reconstruction of boulevard
• Replacing:
water lines with FKAA
sewer lines with city of Key West
seawall, promenade
traffic signals with hurricane-resistant ones
• Installing new:
traffic signal at Searstown
streetlights
landscaping
sidewalks
drainage system
• Maintaining entrances to nearly 170 businesses along construction corridor
For more information, visit www.fdotmonroe.com/keywest or contact spokesman Dean Walters at dean@swcinc.net or 305-849-1474.